CIDB registration fee in Malaysia depends on your contractor grade: from RM20 a year for G1 to RM1,400 a year for G7. This guide is for SME owners who take on construction work and want to know what to pay, when to pay, and what happens if they miss a step. It is based on the registration page and fee schedule (Jadual D) of the Construction Industry Development Board (CIDB).
CIDB registers contractors under the Construction Industry Development Board Malaysia Act 1994 (Act 520). A contractor is anyone who carries out, completes or agrees to carry out construction work. Fees can change, so always check the CIDB website before you pay.
Key Takeaways
- Under Section 25 of Act 520, a contractor must register with CIDB before accepting or carrying out construction work, unless exempted under Section 40(1).
- Breaking Section 25 can bring a fine of not less than RM10,000 and not more than RM100,000 (Section 29).
- The yearly fee for the contractor registration certificate (PPK) goes by grade, from RM20 (G1) to RM1,400 (G7).
- Renewal in the same grade gets a 50% reduction of the registration fee. If the grade changes, the fee for the current grade applies.
- Pay online through CIMS only. Fees are not refunded, and the payment deadlines are short.
CIDB Registration Fee by Grade
CIDB sets the PPK registration fee per year for each grade. A new PPK is valid for up to 2 years from the date you pay the fee. Renewal and re-registration are valid for 1 to 3 years, depending on the CCD points recorded for your company.
| Grade | Fee per year | Fee per year for same-grade renewal (50% reduction) |
|---|---|---|
| G1 | RM20 | RM10 |
| G2 | RM80 | RM40 |
| G3 | RM150 | RM75 |
| G4 | RM350 | RM175 |
| G5 | RM700 | RM350 |
| G6 | RM1,000 | RM500 |
| G7 | RM1,400 | RM700 |
These amounts come from CIDB Jadual D. A separate process fee applies when you submit an application (see Jadual A on the CIDB website). The Special Contractor Certificate (SPKK) has no registration fee.
Other Fees You May Pay
| Situation | Fee |
|---|---|
| Move to a lower grade | RM100 |
| Move to a higher grade | The difference between the new grade fee and the previous grade fee |
| Update of registration or company information that reprints the certificate | RM100 per application |
| Renewal where the grade changes | The fee for the current grade applies |
| Reprint of certificate | Free, printed online |
Deadlines and Payment Rules
Many applications fail because a deadline is missed, not because of the fee itself. These are the rules CIDB states on its registration page:
- You can edit a new application for 14 days from the day it is created. If it is not submitted in that time, it is cancelled automatically.
- Pay the process fee within 7 days of submission, or the application is cancelled automatically.
- Pay the registration fee within 14 days of the approval letter. If not, the approval lapses and you must apply again.
- Pay online through the CIMS system. Cheques are not accepted, and all fees are non-refundable.
- Renew at least 120 days before the expiry date.
- Keep your original supporting documents for 3 years from the application date, in case CIDB checks them.
Worked Example: Renewal for a G3 Contractor
A G3 contractor pays RM150 a year at the normal rate. For a same-grade renewal with the 50% reduction, the fee is RM75 a year. If CIDB approves 3 years, the total is 3 x RM75 = RM225. This is only an illustration. The approval letter shows the exact amount you must pay.
What Happens If Your CIDB Registration Lapses
You must not tender or carry out work after your certificate expires, until it is renewed. You also must not accept work above your grade value or outside your registered category. CIDB can cancel or suspend a registration for reasons such as bankruptcy, a false statement in the application, or abandoning work in progress (Regulation 15 of the Contractor Registration Regulations 1995). Read our guide on CIDB licence renewal for contractors for the renewal steps.
Checklist Before You Pay
- Confirm which grade and category your company needs.
- Check the current fee in Jadual D on the CIDB website.
- Prepare your supporting documents before you start the CIMS application.
- Diarise the 7-day and 14-day payment deadlines.
- Set a reminder to renew 120 days before expiry.
Conclusion
Know your grade, pay on time through CIMS, and renew early. If you are new to CIDB, start with our guide to CIDB Malaysia, and read about the CIDB Green Card for site workers, because all site workers must hold a valid Construction Personnel Card.
How Conzlab can help: Conzlab can help with CIDB contractor registration and renewal applications, including preparing documents and following up on the CIMS system. Contact Conzlab to check which steps apply to your company.
Official Sources
- CIDB: Contractor Registration
- CIDB: Jadual D, Registration Fees and Validity
- CIDB: Renewal Application Form (3.3)
- CIDB: Contractors
Last updated: 13 November 2026. This article is general information, not tax or legal advice. Rules can change, so check with the agency before you act.
Frequently Asked Questions
The PPK fee is set per year by grade: G1 RM20, G2 RM80, G3 RM150, G4 RM350, G5 RM700, G6 RM1,000 and G7 RM1,400, based on CIDB Jadual D. A separate process fee also applies.
Section 25 of Act 520 requires contractors to register before accepting or carrying out construction work, except those exempted under Section 40(1). Check with CIDB if you are unsure whether you are exempt.
No. CIDB states that payment is online through CIMS only, and company or personal cheques are not accepted. Fees are non-refundable.
CIDB says renewal can be made at least 120 days before the expiry date. You must not tender or carry out work after expiry until it is renewed.
CIDB Registration Fee Malaysia: G1 to G7 Fees and Deadlines